County Engineer - Design, Construction & Inspection Guidance

The intent of this page is to provide design, construction, plan approval, permit, and inspection guidance to permittees (permit holders), land owners, developers, engineers, operators, and qualified professionals.  General guidance, by topic, is provided below.

Oldham County Engineer Permit Guidance

A Stormwater Quality Management and Erosion Control Permit Application shall be filled out and submitted for all residential, commercial, and industrial construction projects, regardless of size, within Oldham County (Note:  only an individual residential lot development less than 1-acre, that is not impacting the flood plain or jurisdictional waterways (federal or state), is not required to submit this form).  Once the application is submitted, the Oldham County Engineer will assess the information submitted within the permit to determine if the construction project requires a Stormwater Quality Management and Erosion Control permit.  If a building is being constructed on the construction site, a building permit application shall also be submitted to the Planning and Development Department.  Please use the following link (http://www.oldhamcountyky.gov/oldham-county-building-inspections) to obtain information concerning the Oldham County building permit application and its associated process.  Other Federal, State, and County permits may also be required based on the scope of construction and land-disturbing activity.  In general, if your construction activity is described below, you should check with the U.S. Army Corps of Engineers (US ACE), Kentucky Division of Water (KY DOW), and other County offices to determine if additional permits are needed. 

Construction Activity

Applicable Federal or State Permit

Land disturbing activities > 1-acre. 

KYPDES General Permit from the KY Division of Water. Click here for more information. 

Land disturbing activities less than 1-acre, but part of a larger common plan of development that is greater than 1 acre.

KYPDES General Permit from the KY Division of Water. Click here for more information. 

Land disturbing activity in a stream or river.

Army Corps of Engineers, 404 Permit.  Click here for more information

Land disturbing activity in a stream or river, along a stream or river, across a stream or river, or in a riparian area.

KY Division of Water, 401 Water Quality Certification Permit.
KY Division of Water, Permit to Construct Across or Along a Stream. Click here for more information.

Building of a Dam or Pond

 

KY Division of Water, Permit to Construct Across or Along a Stream  Click here for more information

Land disturbing activity in a flood plain.

KY Division of Water, Permit to Construct Across or Along a Stream.  Click here for more information.

Oldham County Planning and Development (Flood Plain Coordinator), Permit to Develop in a Flood Hazard Area. Click here for information.  

It is the responsibility of the land owner, developer, and engineer to ensure that all permits are obtained.  All Federal and State permits (with associated supporting information) shall be provided to the Oldham County Engineer as part of the plan review and Stormwater Quality Management and Erosion Control Permit process. 

Oldham County Development and Construction Process Guidance

Land owners and developers will generally commence the process of developing or subdividing land by contacting the Oldham County Planning and Development Office.  Once a land owner or developer has obtained approval from the Oldham County Planning Commission and/or legislative body for their project, they shall submit their construction plans and calculations to the Oldham County Engineer for approval.  Construction plans and calculations shall be submitted with a Stormwater Quality Management and Erosion Control Permit Application to the Oldham County Engineer. 

Construction Plan Review and Approval Guidance

Once the Oldham County Engineer receives a “complete” submission of construction plans and calculations and Stormwater Quality Management and Erosion Control Permit Application, they will be placed in the queue for review.  In general, the Oldham County Engineer strives to have construction plans and calculations reviewed and returned to the submitter within four (4) weeks.  However, this timeframe will vary based on the complexity of the construction project, the accuracy and compliance of the plans when compared to Oldham County regulations and accepted engineering standards, and number of construction projects in the queue for review.  To expedite plan review, engineers should ensure plans and calculations are complete, sufficiently detailed, and conform to all Oldham County regulations and accepted engineering standards.

Oldham County Design and Plan Review Checklists

To assist owners, land developers, and design engineers in submitting construction plans that are complete and in compliance with accepted engineering design principles and requirements outlined in Oldham County ordinances or other acceptable legislative/regulatory agencies, the Oldham County Engineer has developed the below design and plan review checklists.  These checklists are not a comprehensive list of design principles or plan content and will not guarantee plan approval when used.  It represents the minimum level of design and plan content required by the Oldham County Engineer’s Office and shall be used by owners, land developers, and design engineers in locating and applying accepted and/or recommended engineering design principles and regulatory standards to design and plan submissions.  It is the sole responsibility of the owners, land developers, and design engineers to ensure that construction plans comply with all required laws, codes, ordinances, regulations, and accepted engineering design principles.  The appropriate checklist(s) are required to be submitted with the plans and permit application.  Submittals without accompanying checklists will not be accepted.

  1. Complete Design and Plan Review Checklist Document
  2. Checklist 1 – General Plan Content Checklist
  3. Checklist 2 – Cover Sheet Checklist
  4. Checklist 3 – Site (Layout) Plan Checklist
  5. Checklist 4 – Grading Plan Checklist
  6. Checklist 5 – Erosion Prevention and Sediment Control (EPSC) Plan Checklist
  7. Checklist 6 – Drainage Calculations Checklist
  8. Checklist 7 – Drainage Plan Checklist
  9. Checklist 8 – Stormwater Layout Plan Checklist
  10. Checklist 9 – Stormwater Profile Plan Checklist
  11. Checklist 10 – Road Profile Plan Checklist
  12. Checklist 11 – Intersection Grading Plan Checklist
  13. Checklist 12 – Details Plan Checklist

Starting Land-Disturbing Activities (Pre-Construction Meeting & Perimeter Control)

Once construction plans have been approved, a Stormwater Quality Management and Erosion Control Permit has been issued (or deemed not required), and the project has been bonded, land-disturbing activities shall be initiated by conducting the required Pre-Construction Meeting.  This meeting is attended by the permittee (permit holder), project engineer, construction site operators, qualified professional (sediment and erosion control professional), and representatives of the Oldham County Engineer’s Office in order to review the approved permit, SWPPP, EPSC Plan, and construction plans.  Following the Pre-Construction Meeting the permittee shall commence land-disturbing activities by first implementing all perimeter erosion prevention and sediment control (EPSC) measures (also known as BMPs).

Permittee-Conducted Construction Site Inspections

Once land-disturbing activities have commenced, the permittee (permit holder) is responsible for proper implementation, inspection, and maintenance of the erosion prevention and sediment control (EPSC) devices (also known as BMPs) throughout the duration of the construction project until the Stormwater Quality Management and Erosion Control Permit is terminated, in writing, by the Oldham County Engineer.  All Permittee-Conducted Inspections shall be conducted by a Qualified Professional.  The Qualified Professional shall use Oldham County’s Stormwater Construction Inspection Report to document all inspections.

Common Deficiencies and Violations Found at Construction Sites

The Oldham County Engineer Office conducts its own inspections of construction sites to ensure the permit holder is complying with the terms of the permit and approved construction plans.  Below are a few of the more common discrepancies and violations that Oldham County inspectors encounter during inspections.  Permit holders, qualified inspectors, and operators of construction sites should be familiar with identifying and correcting these common discrepancies.  Click on each link for more information.

  1. Silt Fence
  2. Concrete Washout

To prevent these and other deficiencies and violations, Permit holders, land owners, engineers, qualified inspectors, and operators of construction sites should be familiar with the following guidance manuals.

1) Kentucky Erosion Prevention and Sediment Control Field Guide,

2) Kentucky Best Management Practices (BMPs) for Controlling Erosion, Sediment, and Pollution Runoff from Construction Sites (2009)